Monday, June 29, 2009

New and Improved Fuller and Grand

The intersection of Fuller Rd and Grand Avenue is now open for travel on the south, west, and east sides. The north leg is still closed for the next phase of the Grand Avenue project. This project is part of a larger reconstruction of Grand Avenue from the Raccoon River Park entrance to Railroad Avenue as a four and five-lane section. The new intersection allows for safer traffic movements through the intersection and roadway, and includes traffic signals.


Although the intersection officially opened up last Wednesday afternoon, we had to close it again at times on Friday, Saturday, and Sunday for Hy-Vee elite and age group races.







Grand Avenue was originally paved in the early 1930s, so this rehabilitation is very much needed. The overall project involves a widening of the street to increase traffic capacity and wider lanes (12 feet). All three phases are described below.

Phase 1: This phase of the overall project involved reconstruction of the Grand Avenue/Fuller Road intersection, including the installation of signals. Construction in 2008 included relocation of public utilities as well as construction of the retaining wall south of Heatherwood Drive. Construction began March 23, 2009 for the 2009 Construction season and involved the remaining utility work, full pavement removal and replacement, and construction of new traffic signals at the Grand/Fuller intersection.

Phase 2: This phase will include construction of the four and five-lane section of Grand Avenue from the limits of Phase One northerly to the railroad tracks north of Delevan Drive. Phase Two will be constructed during the 2009 construction season.

Phase 3: This phase includes construction of a similar pavement section from the limits of Phase One southerly to just beyond the entrance to Raccoon River Park. The construction timelime for Phase Three is yet to be determined.